Current and Upcoming Works

Kingborough Council is responsible for the municipality’s roads, reserves, sports facilities, stormwater systems and solid waste management. In order to maintain the local infrastructure, we undertake a schedule of planned works every year. These works are a combination of ongoing maintenance work, as well as new capital projects.

We aim to provide an overview of works currently in the pipeline.

Dates and times are supplied with the best of accuracy but may change without notice . If start and completion dates are unknown at this stage a default financial year timeframe is set.

 

Project Name Address Schedule of Works Activity Type More Info
Esplanade (vic2-4) Snug Footpath 2 Esplanade, Snug 06/07/2026 - 30/11/2026 New footpath on Esplanade, Snug connecting Channel Hwy and Cutana Parade New
Hutchins Street (vic8-10) footpath upgrade Hutchins Street, Kingston 05/06/2026 - 10/07/2026 Upgrade and renew footpath on Hutchins Street (vic 8-10) Upgrade More information
Campbell Street stormwater upgrade Campbell Street, Kingston 03/08/2026 - 30/11/2026 Stormwater upgrade works to improve system capacity Upgrade
Adventure Bay Road footpath (vic 964-996) Adventure Bay Road, Adventure Bay 01/06/2026 - 31/12/2026 New footpath on Adventure Bay Road (vic 964-996) New
Auburn Rd to Beach Rd stormwater improvement (vicinity 84 Beach Rd) 84 Beach Road, Kingston 01/07/2026 - 30/11/2026 Stormwater improvements vicinity 84 Beach Road Upgrade
Lightwood Park access link (carpark to new pavilion) Kingborough Sports Centre 02/03/2026 - 30/06/2026 New access path at Lightwood Park New
Wyburton Place and Clare Street reconstruction Clare Street, Margate 01/04/2026 - 31/12/2026 Reconstruction and sealing of Wyburton Place and Clare Street Upgrade
Kingston Beach Foreshore Rehabilitation Osborne Esplanade, Kingston Beach 01/07/2026 - 30/11/2026 Final decking, beach access and landscaping works. Upgrade
Alamo Close play space and parkland works Alamo Close, Blackmans Bay 01/07/2026 - 31/10/2026 New play space and parkland works. Upgrade
Davies Road reconstruction Davies Road, Lower Snug 01/10/2025 - 30/06/2026 Reconstruction of Davies Road including stormwater upgrades and new footpath. Upgrade
Church St/Beach Rd junction signalisation Church Street, Kingston 04/01/2027 - 31/03/2027 Signalisation and associated works at the Church Street / Beach Road junction. Upgrade
Baringa Road/Wandella Road stormwater upgrade Baringa Road, Taroona 04/05/2026 - 30/06/2026 Stormwater upgrades at Baringa Road and Wandella Road, Taroona Upgrade
Sherburd Oval Change Rooms Brightwater Road, Blackmans Bay 01/07/2026 - 30/06/2027 New change room facilities at Sherburd Oval, Blackmans Bay New
Taroona bike lanes upgrade Channel Highway, Taroona 01/09/2026 - 31/12/2026 Upgrade bike lanes on the Channel Highway through Taroona. Better Active Transport Grant Program. Upgrade
Browns Road reconstruction - stage 2 1-19 Browns Road, Kingston 03/03/2025 - 31/07/2026 Road reconstruction including new concrete footpath Upgrade More information