Planning Process

An indicative diagram of the stages of the planning process are laid out below.

As with any detailed process, the below is provided as a guide. It is important to note that there are many variables to consider and that they will directly effect the timelines for your planning project.

Application for planning permit

You submit the application, including all relevant documentation and fees.

Our information on how to submit a planning application will guide you through the requirements, as well as any additional items to consider.

Lodgement

Your submission will be assessed to ensure all initial documentation has been provided with your application and contact you if further information is required.

Kingborough Council’s Customer Service team will then lodge the application and send you the invoice to pay. Once it is paid, the application will be allocated to a Planning Officer for assessment.

Preliminary assessment

We will refer your application to other council employees, including, but not limited to: a Development Engineering Officer, Environmental Planner, Plumbing Officer, Environmental Health Officer, and Urban Designer.

Once these officers have completed their initial assessment of your proposal we will determine whether further information is required to advertise and/or assess your development.

If we need more information we will let you know in a timely manner. Planning officers have up to 21 days in which to request further information for discretionary planning applications and 14 days for permitted planning applications.

Advertising period

Your application may require advertising, pursuant to the requirements of the Act.

Members of the public have 14 days from the date of advertisement to lodge a representation with Council (as per the representation expiry date).  This must be done in writing and should state the reasons why they support or object to the application.

Discretionary planning applications are able to be viewed within the advertising period either online or in person at the Civic Centre in Kingston.

 

Detailed assessment

The time assessment takes varies depending on the size and complexity of the project.

Assessment against the planning scheme provisions must be made. Planners consider both internal, and external referrals, and representations made by members of the public, either for or against the proposal.

Council meeting

Planning applications may need to be presented to the Councillors, who act as the planning authority, for determination at a council meeting.

Planning applications need to be presented to the Councillors if a representation has been received. An extension of time may need to be requested in order to present an application to the Councillors within the statutory timeframe of 42 days.

For full council meeting details, dates and agendas, visit the Council Meetings webpage.

Decision

We will issue a notice of our decision to approve or refuse the application.